Keyword: MMI
Paper Title Other Keywords Page
MOPOST006 Beam Commissioning and Optimisation in the CERN Proton Synchrotron After the Upgrade of the LHC Injectors vacuum, proton, operation, synchrotron 54
 
  • A. Huschauer, M.R. Coly, D.G. Cotte, H. Damerau, M. Delrieux, J.-C. Dumont, Y. Dutheil, S.E.R. Easton, M.A. Fraser, O. Hans, G.I. Imesch, S. Joly, A. Lasheen, C.L. Lombard, R. Maillet, B. Mikulec, J.-M. Nonglaton, S. Sainz Perez, B. Salvant, R. Suykerbuyk, F. Tecker, R. Valera Teruel
    CERN, Meyrin, Switzerland
 
  The CERN LHC injector chain underwent a major upgrade during the Long Shutdown 2 (LS2) in the framework of the LHC Injectors Upgrade (LIU) project. After 2 years of installation work, the Proton Synchrotron (PS) was restarted in 2021 with the goal to achieve pre-LS2 beam quality by the end of 2021. This contribution details the main beam commissioning milestones, encountered difficulties and lessons learned. The status of the fixed-target and LHC beams will be given and improvements in terms of performance, controls and tools described.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-MOPOST006  
About • Received ※ 01 June 2022 — Revised ※ 14 June 2022 — Accepted ※ 15 June 2022 — Issue date ※ 02 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPOST007 Summary of the First Fully Operational Run of LINAC4 at CERN linac, operation, cavity, injection 58
 
  • P.K. Skowroński, G. Bellodi, B. Bielawski, R.B. Borner, G.P. Di Giovanni, E. Gousiou, J.-B. Lallement, A.M. Lombardi, B. Mikulec, J. Parra-Lopez, F. Roncarolo, J.L. Sanchez Alvarez, R. Scrivens, L. Timeo, R. Wegner
    CERN, Meyrin, Switzerland
 
  In December 2020 the newly commissioned LINAC4 started delivering beam for the CERN proton accelerator chain, replacing the old LINAC2. LINAC4 is a 352 MHz normal conducting linac, providing a beam of negative hydrogen ions at 160 MeV that are converted into protons at injection into the PS Booster synchrotron. In this paper we report on the achieved beam performance, availability, reproducibility and other operational aspects of LINAC4 during its first fully operational year. We also present the machine developments performed and the plans for future improvements.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-MOPOST007  
About • Received ※ 09 June 2022 — Revised ※ 10 June 2022 — Accepted ※ 16 June 2022 — Issue date ※ 04 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPOST010 Deuteron Beam Power Ramp-Up at SPIRAL2 linac, MEBT, cavity, LEBT 70
 
  • A.K. Orduz, M. Di Giacomo, R. Ferdinand, J.-M. Lagniel, G. Normand
    GANIL, Caen, France
  • D.U. Uriot
    CEA-IRFU, Gif-sur-Yvette, France
 
  The SPIRAL2 linac commissioning started on 8 July 2019 after obtaining the authorisation to operate by the French Safety Authority. The tuning of the two Low Energy Beam Transport (LEBT), Radio Frequency Quadrupole (RFQ), Medium Energy Beam Transport (MEBT), Superconducting (SC) linac and High Energy Beam Transport (HEBT) was done with H+, 4He2+ and D+ beams during three periods of six months each in 2019, 2020 and 2021. The results obtained in 2021 with a D+ beam are presented. The strategy for the tuning of the MEBT, including three rebunchers, is described. The comparison between the beam parameter measurements and reference simulations are also presented. The main results of the power ramp-up to 10 kW in the linac with a 5 mA D+ beam are next reported. Finally, the extrapolation from the nominal power (200 kW) to the obtained results is analysed.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-MOPOST010  
About • Received ※ 08 June 2022 — Revised ※ 13 June 2022 — Accepted ※ 16 June 2022 — Issue date ※ 18 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPOST021 ReAccelerator Upgrade, Commissioning and First Experiments at the National Superconducting Cyclotron Laboratory (NSCL) / Facility for Rare Isotope Beams (FRIB) cryomodule, experiment, linac, ion-source 101
 
  • A.C.C. Villari, G. Bollen, K.D. Davidson, K. Fukushima, A.I. Henriques, K. Holland, S.H. Kim, A. Lapierre, T. Maruta, D.G. Morris, S. Nash, P.N. Ostroumov, A.S. Plastun, J. Priller, B.M. Sherrill, R. Walker, T. Zhang, Q. Zhao
    FRIB, East Lansing, Michigan, USA
  • B. Arend, D.B. Crisp, D.J. Morrissey, M. Steiner
    NSCL, East Lansing, Michigan, USA
 
  Funding: Work supported by the NSF under grant PHY15-65546 and DOE-SC under award number DE-SC0000661
The reaccelerator ReA is a state-of-the-art super-conducting linac for reaccelerating rare isotope beams produced via inflight fragmentation or fission and subse-quent beam stopping. ReA was subject of an upgrade that increased its final beam energy from 3 MeV/u to 6 MeV/u for ions with charge over mass equal to 1/4. The upgrade included a new room-temperature rebuncher after the first section of acceleration, a new β = 0.085 QWR cryomodule and two new beamlines in a new ex-perimental vault. During commissioning, beams were accelerated with near 100 percent transport efficiency through the linac and delivered through beam transport lines. Measured beam characteristics match those calcu-lated. Following commissioning, stable and long living rare isotope beams from a Batch Mode Ion Source (BMIS) were accelerated and delivered to experiments. This con-tribution will briefly describe the upgrade, and results from beam commissioning and beam delivery for experi-ments.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-MOPOST021  
About • Received ※ 07 June 2022 — Revised ※ 12 June 2022 — Accepted ※ 17 June 2022 — Issue date ※ 21 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPOST022 Upgrade of the Radio Frequency Quadrupole of the ReAccelerator at NSCL/FRIB rfq, operation, vacuum, RF-structure 104
 
  • A.S. Plastun, J. Brandon, A.I. Henriques, S.H. Kim, D.G. Morris, S. Nash, P.N. Ostroumov, A.C.C. Villari, Q. Zhao, S. Zhao
    FRIB, East Lansing, Michigan, USA
  • D.B. Crisp, D.P. Sanderson
    NSCL, East Lansing, Michigan, USA
 
  Funding: Work supported by the National Science Foundation under grant PHY15-65546
The ReA-RFQ is a four-rod room-temperature structure aimed to be the first step acceleration of rare isotopes as well as stable beams before injection into the ReA SRF linac. The beams of charge to mass ratios of 1/5 to 1/2 from the Electron Beam Ion Trap at 12 keV/u should be accelerated to at least 500 keV/u to be efficiently accelerated in the main SRF linac. Since the commissioning of the original ReA RFQ in 2010 the design voltage has never been reached, and CW operation was never achieved due to cooling issues. In 2016 a new design including trapezoidal modulation was proposed, which permitted achieving increased reliability, and would allow reaching the original required specifications. The proposed new rods were built and installed in 2019 and commissioned in the same year. Since then, the RFQ has been working very successfully. Recently it was opened for inspection and verification of its internal status. No damage and discoloration were observed. This contribution will describe the RFQ rebuild process, involving specific RF protections and other technical aspects related to the assembly of the structure. Results of the operation with a variety of beams will be presented.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-MOPOST022  
About • Received ※ 07 June 2022 — Revised ※ 09 June 2022 — Accepted ※ 16 June 2022 — Issue date ※ 11 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPOST035 Operational Experience and Performance of the REX/HIE-ISOLDE Linac ISOL, linac, experiment, operation 140
 
  • J.A. Rodriguez, N. Bidault, E. Fadakis, P. Fernier, M.L. Lozano, S. Mataguez, E. Piselli, E. Siesling
    CERN, Meyrin, Switzerland
 
  Located at CERN, ISOLDE is one of the world’s lead-ing research facilities in the field of nuclear science. Radioactive Ion Beams (RIBs) are produced when 1.4 GeV protons transferred from the Proton Synchrotron Booster (PSB) to the facility impinge on one of the two available targets. The RIB of interest is extracted, mass-separated and transported to one of the experimental stations, either directly, or after being accelerated in the REX/HIE-ISOLDE post-accelerator. In addition to a Penning trap (REXTRAP) to accumulate and transversely cool the beam and a charge breeder (REXEBIS) to boost the charge state of the ions, the post-accelerator includes a linac with both room temperature (REX linac) and superconducting (HIE-ISOLDE linac) sections followed by three HEBT lines to deliver the beam to the different experimental stations. The latest upgrades of the facility as well as a comprehensive list of the RIBs delivered to the users of the facility and the operational experience gained during the last physics campaigns will be presented in this contribution.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-MOPOST035  
About • Received ※ 07 June 2022 — Revised ※ 12 June 2022 — Accepted ※ 13 June 2022 — Issue date ※ 21 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPOPT006 Characterization of the Electron Beam Visualization Stations of the ThomX Accelerator HOM, target, diagnostics, controls 240
 
  • A. Moutardier, C. Bruni, J-N. Cayla, I. Chaikovska, S. Chancé, N. Delerue, H. Guler, H. Monard, M. Omeich, S.D. Williams
    Université Paris-Saclay, CNRS/IN2P3, IJCLab, Orsay, France
  • S.D. Williams
    The University of Melbourne, Melbourne, Victoria, Australia
 
  Funding: Research Agency under the Equipex convention ANR-10-EQPX-0051.
We present an overview of the diagnostics screens stations - named SSTs - of the ThomX compact Compton source. ThomX is a compact light source based on Compton backscattering. It features a linac and a storage ring in which the electrons have an energy of 50 MeV. Each SST is composed of three screens, a YAG:Ce screen and an Optical Transition Radiation (OTR) screen for transverse measurements and a calibration target for magnification and resolution characterisation. The optical system is based on commercial lenses that have been reverse-engineered. An Arduino is used to control both the aperture and the focus remotely, while the magnification must be modified using an external motor. We report on the overall performance of the station as measured during the first steps of beam commissioning and on the optical system remote operations.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-MOPOPT006  
About • Received ※ 20 May 2022 — Revised ※ 10 June 2022 — Accepted ※ 14 June 2022 — Issue date ※ 17 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPOPT040 Summary of the Post-Long Shutdown 2 LHC Hardware Commissioning Campaign dipole, operation, target, hardware 335
 
  • A. Apollonio, O.O. Andreassen, A. Antoine, T. Argyropoulos, M.C. Bastos, M. Bednarek, B. Bordini, K. Brodzinski, A. Calia, Z. Charifoulline, G.-J. Coelingh, G. D’Angelo, D. Delikaris, R. Denz, L. Fiscarelli, V. Froidbise, M.A. Galilée, J.C. Garnier, R. Gorbonosov, P. Hagen, M. Hostettler, D. Jacquet, S. Le Naour, D. Mirarchi, V. Montabonnet, B.I. Panev, T.H.B. Persson, T. Podzorny, M. Pojer, E. Ravaioli, F. Rodriguez-Mateos, A.P. Siemko, M. Solfaroli, J. Spasic, A. Stanisz, J. Steckert, R. Steerenberg, S. Sudak, H. Thiesen, E. Todesco, G. Trad, J.A. Uythoven, S. Uznanski, A.P. Verweij, J. Wenninger, G.P. Willering, D. Wollmann, S. Yammine
    CERN, Meyrin, Switzerland
  • V. Vizziello
    INFN/LASA, Segrate (MI), Italy
 
  In this contribution we provide a summary of the LHC hardware commissioning campaign following the second CERN Long Shutdown (LS2), initially targeting the nominal LHC energy of 7 TeV. A summary of the test procedures and tools used for testing the LHC superconducting circuits is given, together with statistics on the successful test execution. The paper then focuses on the experience and observations during the main dipole training campaign, describing the encountered problems, the related analysis and mitigation measures, ultimately leading to the decision to reduce the energy target to 6.8 TeV. The re-commissioning of two powering sectors, following the identified problems, is discussed in detail. The paper concludes with an outlook to the future hardware commissioning campaigns, discussing the lessons learnt and possible strategies moving forward.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-MOPOPT040  
About • Received ※ 08 June 2022 — Revised ※ 13 June 2022 — Accepted ※ 16 June 2022 — Issue date ※ 27 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPOPT047 Experimental Demonstration of Machine Learning Application in LHC Optics Commissioning optics, quadrupole, simulation, diagnostics 359
 
  • E. Fol, F.S. Carlier, J. Dilly, M. Hofer, J. Keintzel, M. Le Garrec, E.H. Maclean, T.H.B. Persson, F. Soubelet, R. Tomás García, A. Wegscheider
    CERN, Meyrin, Switzerland
  • J.F. Cardona
    UNAL, Bogota D.C, Colombia
 
  Recently, we conducted successful studies on the suitability of machine learning (ML) methods for optics measurements and corrections, incorporating novel ML-based methods for local optics corrections and reconstruction of optics functions. After performing extensive verifications on simulations and past measurement data, the newly developed techniques became operational in the LHC commissioning 2022. We present the experimental results obtained with the ML-based methods and discuss future improvements. Besides, we also report on improving the Beam Position Monitor (BPM) diagnostics with the help of the anomaly detection technique capable to identify malfunctioning BPMs along with their possible fault causes.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-MOPOPT047  
About • Received ※ 07 June 2022 — Accepted ※ 16 June 2022 — Issue date ※ 06 July 2022  
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPOPT056 Commissioning of a Gas Jet Beam Profile Monitor for EBTS and LHC electron, photon, simulation, vacuum 393
 
  • H.D. Zhang, N. Kumar, A. Salehilashkajani, O. Sedláček, C.P. Welsch
    Cockcroft Institute, Warrington, Cheshire, United Kingdom
  • M. Ady, T. Lefèvre, S. Mazzoni, I. Papazoglou, A. Rossi, G. Schneider, O. Sedláček, K. Sidorowski, R. Veness
    CERN, Meyrin, Switzerland
  • P. Forck, S. Udrea
    GSI, Darmstadt, Germany
  • N. Kumar, A. Salehilashkajani, O. Sedláček, O. Stringer, C.P. Welsch, H.D. Zhang
    The University of Liverpool, Liverpool, United Kingdom
 
  Funding: This work is supported by the HL-LHC-UK II project funded by STFC and CERN and the STFC Cockcroft core grant No. ST/G008248/1.
A gas jet beam profile monitor was designed for measuring the electron beam at the electron beam test stand (EBTS) for the Hollow electron lens (HEL) and the proton beam in the large hadron collider (LHC). It is partially installed in the LHC during the second long shutdown. The current monitor is tailored to the accelerator environment including vacuum, geometry, and magnetic field for both the EBTS and the LHC. It features a compact design, a higher gas jet density, and a wider curtain size for a better integration time and a larger detecting range. In this contribution, the commissioning of this monitor at the Cockcroft Institute will be discussed.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-MOPOPT056  
About • Received ※ 08 June 2022 — Accepted ※ 16 June 2022 — Issue date ※ 23 June 2022  
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPOTK004 Status of the Soleil Upgrade Lattice Robustness Studies lattice, injection, simulation, optics 433
 
  • O.R. Blanco-García
    INFN/LNF, Frascati, Italy
  • D. Amorim, A. Loulergue, L.S. Nadolski, R. Nagaoka
    SOLEIL, Gif-sur-Yvette, France
  • M.A. Deniaud
    JAI, Egham, Surrey, United Kingdom
 
  The SOLEIL synchrotron has entered its Technical Design Report (TDR) phase for the upgrade of its storage ring to a fourth generation synchrotron light source. Verification of the equipment specifications (alignment, magnets, power supplies, BPMs), and the methodology for optics corrections are critical in order to ensure the feasibility of rapid commissioning restoring full performance for daily operations. The end-to-end simulation, from beam threading in the first turns to beam storage and stacking, should be handled with a comprehensive model close to the actual commissioning procedure, taking into account all practical steps. During 2021 and 2022, the CDR lattice has undergone significant modifications in response to additional constraints. In this paper, we present an update of the robustness studies for the TDR baseline lattice.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-MOPOTK004  
About • Received ※ 07 June 2022 — Revised ※ 14 June 2022 — Accepted ※ 17 June 2022 — Issue date ※ 05 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPOMS014 Commissioning of a High-Gradient X-Band RF Gun Powered by Short RF Pulses from a Wakefield Accelerator gun, electron, laser, cathode 652
 
  • W.H. Tan, X. Lu, P. Piot
    Northern Illinois University, DeKalb, Illinois, USA
  • S.P. Antipov, C.-J. Jing, E.W. Knight, S.V. Kuzikov
    Euclid TechLabs, Solon, Ohio, USA
  • D.S. Doran, G. Ha, C.-J. Jing, W. Liu, X. Lu, P. Piot, P. Piot, J.G. Power, J. Shao, C. Whiteford, E.E. Wisniewski
    ANL, Lemont, Illinois, USA
 
  Funding: This work is supported by the U.S. DOE, under award No. DE-SC0018656 to NIU, DOE SBIR grant No DE-SC0018709 at Euclid Techlabs LLC, and contract No. DE-AC02-06CH11357 with ANL.
A high-gradient X-band (11.7-GHz) photoinjector developed by Euclid Techlabs, was recently commissioned at the Argonne Wakefield Accelerator (AWA). The system comprises a 1+1/2-cell RF gun powered by short RF pulses generated as a train of high-charge bunches from the AWA accelerator passes through a slow-wave power extraction and transfer structure. The RF photoinjector was reliably operating with electric fields in excess of 300 MV/m on the photocathode surface free of breakdown and with an insignificant dark-current level. We report on the RF-gun setup, commissioning, and the associated beam generation via photoemission.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-MOPOMS014  
About • Received ※ 08 June 2022 — Revised ※ 12 June 2022 — Accepted ※ 18 June 2022 — Issue date ※ 19 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPOMS048 Fast Trigger System for Beam Abort System in SuperKEKB hardware, kicker, detector, power-supply 754
 
  • H. Ikeda, T. Mimashi, S. Nakamura, T. Oki, S. Sasaki
    KEK, Ibaraki, Japan
 
  In order to protect the hardware components of the de-tector and accelerator from sudden beam loss of high beam currents, the fast beam abort system is developed in the SuperKEKB. The previous abort system was not fast enough for sudden beam loss that caused QCS quench, and it gave a damage to the collimator and the Belle-II detector. A fast abort system is required to pre-venting such damage. The abort system consists of sev-eral sensors that generate interlock signal (the loss moni-tor, dose in the Bell-II detector, and the magnet failure etc.), optical cable system to transfer the interlock signal to central control room (CCR), the abort trigger signal generation system and the abort kicker. To reduce total time, we reduce transmission time from local control room to CCR by changing signal cable route. Since the interlock signal produced by magnet power supply was slow, we modified the magnet power supply. For more quick generation of abort trigger signal, we increased number of the abort gap. By these improvements, an average abort time is reduced from 31µsec to 25µsec. This improvement looks small, but it brought preventing the serious radiation damage to many hardware compo-nents. Detail of the system and result is presented in this paper.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-MOPOMS048  
About • Received ※ 08 June 2022 — Revised ※ 12 June 2022 — Accepted ※ 14 June 2022 — Issue date ※ 10 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUOXSP1 Origin and Mitigation of the Beam-Induced Surface Modifications of the LHC Beam Screens electron, radiation, cryogenics, ECR 780
 
  • V. Petit, P. Chiggiato, M. Himmerlich, S. Marinoni, H. Neupert, M. Taborelli, L.J. Tavian
    CERN, Meyrin, Switzerland
 
  All over Run 2, the LHC beam-induced heat load on the cryogenic system exhibited a wide scattering along the ring. Studies ascribed the heat source to electron cloud build-up, indicating an unexpected high Secondary Electron Yield (SEY) of the beam screen surface in some LHC regions. The inner copper surface of high and low heat load beam screens, extracted during the Long Shutdown 2, was analysed. On the low heat load ones, the surface was covered with the native Cu2O oxide, while on the high heat load ones CuO dominated at surface, and it exhibited a very low carbon coverage. Such chemical modifications increase the SEY and inhibit a proper conditioning of the affected surfaces. Following this characterisation, the mechanisms for CuO build-up in the LHC beam pipe were investigated on a newly commissioned cryogenic system allowing electron irradiation, surface chemical characterisation by X-ray Photoelectron Spectroscopy and SEY measurements on samples held below 15 K. In parallel, curative solutions against the presence of CuO in the LHC beam screens were explored, which could be implemented in-situ to recover a proper conditioning and lower the beam-induced heat load.  
slides icon Slides TUOXSP1 [2.669 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-TUOXSP1  
About • Received ※ 17 May 2022 — Revised ※ 10 June 2022 — Accepted ※ 17 June 2022 — Issue date ※ 05 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUIYGD3 FRIB Commissioning and Early Operations linac, target, controls, operation 802
 
  • J. Wei, H. Ao, S. Beher, G. Bollen, N.K. Bultman, F. Casagrande, W. Chang, Y. Choi, S. Cogan, C. Compton, M. Cortesi, J.C. Curtin, K.D. Davidson, X.-J. Du, K. Elliott, B. Ewert, A. Facco, A. Fila, K. Fukushima, V. Ganni, A. Ganshyn, T. Glasmacher, J.-W. Guo, Y. Hao, W. Hartung, N.M. Hasan, M. Hausmann, K. Holland, H.-C. Hseuh, M. Ikegami, D.D. Jager, S. Jones, N. Joseph, T. Kanemura, S.H. Kim, C. Knowles, P. Knudsen, T. Konomi, B.R. Kortum, T. Lange, M. Larmann, T.L. Larter, K. Laturkar, R.E. Laxdal, J. LeTourneau, Z. Li, S.M. Lidia, G. Machicoane, C. Magsig, P.E. Manwiller, F. Marti, T. Maruta, E.S. Metzgar, S.J. Miller, Y. Momozaki, D.G. Morris, M. Mugerian, I.N. Nesterenko, C. Nguyen, P.N. Ostroumov, M.S. Patil, A.S. Plastun, J.T. Popielarski, L. Popielarski, M. Portillo, J. Priller, X. Rao, M.A. Reaume, H.T. Ren, K. Saito, B.M. Sherrill, A. Stolz, B.P. Tousignant, R. Walker, X. Wang, J.D. Wenstrom, G. West, K. Witgen, M. Wright, T. Xu, T. Xu, Y. Yamazaki, T. Zhang, Q. Zhao, S. Zhao
    FRIB, East Lansing, Michigan, USA
  • B. Arend, T.N. Ginter, E. Kwan, M.K. Smith, M. Steiner, O. Tarasov
    NSCL, East Lansing, Michigan, USA
  • A. Facco
    INFN/LNL, Legnaro (PD), Italy
  • K. Hosoyama
    KEK, Ibaraki, Japan
  • M.P. Kelly, Y. Momozaki
    ANL, Lemont, Illinois, USA
  • R.E. Laxdal
    TRIUMF, Vancouver, Canada
  • M. Wiseman
    JLab, Newport News, Virginia, USA
 
  Funding: Work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661.
The Facility for Rare Isotope Beams (FRIB) project has completed technical construction in January 2022, five months ahead of schedule baselined about 10 years ago. Beam commissioning has been planned in seven phases starting from 2017 when the normal-conducting ion source and RFQ were commissioned. In April 2021, FRIB driver linac commissioning was completed with heavy ion beams being accelerated to energies above 200 MeV/u using 324 superconducting radiofrequency (SRF) resonators contained in 46 cryomodules. In preparation for high-power operations, a liquid lithium charge strip-per was used to strip uranium beam from average charge state of 33+ to 78+, and multiple charge states were accelerated simultaneously in the linac. By January 2022, FRIB target and fragment separator commissioning was completed with rare-isotope beams produced and identified. In May 2022, the first FRIB user scientific experiment was successfully conducted. This talk summarizes the FRIB accelerator project commissioning and early operations experience with discussions on strategic planning, operational envelope conformance, technical risk mitigation, and lessons learned.
 
slides icon Slides TUIYGD3 [23.483 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-TUIYGD3  
About • Received ※ 07 June 2022 — Revised ※ 10 June 2022 — Accepted ※ 17 June 2022 — Issue date ※ 06 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOST015 Commissioning and First Results of an X-Band LLRF System for TEX Test Facility at LNF-INFN LLRF, klystron, GUI, network 876
 
  • L. Piersanti, D. Alesini, M. Bellaveglia, S. Bini, B. Buonomo, F. Cardelli, C. Di Giulio, E. Di Pasquale, M. Diomede, L. Faillace, A. Falone, G. Franzini, A. Gallo, G. Giannetti, A. Liedl, D. Moriggi, S. Pioli, S. Quaglia, L. Sabbatini, M. Scampati, G. Scarselletta, A. Stella, S. Tocci, L. Zelinotti
    LNF-INFN, Frascati, Italy
 
  Funding: Latino is a project co-funded by Regione Lazio within POR-FESR 2014-2020 program
In the framework of LATINO project (Laboratory in Advanced Technologies for INnOvation) funded by Lazio regional government, the commissioning of the TEst stand for X-band (TEX) facility has started in 2021 at Frascati National Laboratories of INFN. Born as a collaboration with CERN to test high gradient accelerating structures, during 2022 TEX aims at feeding the first EuPRAXIA@SPARC_LAB X-band structure prototype. During 2021 the commissioning has been successfully carried out up to 48 MW. The power unit is driven by an X-band low level RF system, that employs a commercial S-band (2.856 GHz) Libera digital LLRF (manufactured by Instrumentation Technologies), with an up/down conversion stage and a reference generation and distribution system able to produce coherent frequencies for the American S-band and European X-band (11.994 GHz), both designed and realized at LNF. The performance of the system, with a particular focus on amplitude and phase resolution, together with klystron and driver amplifier jitter measurements, will be reviewed in this paper. Moreover, considerations on its suitability and main limitations in view of EuPRAXIA@SPARC_LAB project will be discussed.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-TUPOST015  
About • Received ※ 20 May 2022 — Revised ※ 13 June 2022 — Accepted ※ 17 June 2022 — Issue date ※ 28 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOST025 Beam Commissioning of the New Digital Low-Level RF System for CERN’s AD LLRF, operation, timing, proton 911
 
  • M.E. Angoletta, S.C.P. Albright, D. Barrientos, A. Findlay, M. Jaussi, A. Rey, M. Sumiński
    CERN, Meyrin, Switzerland
 
  CERN’s Antiproton Decelerator (AD) has been re-furbished to provide reliable operation for the Extra Low ENergy Antiproton ring (ELENA). In particular, AD was equipped with a new digital Low-Level RF (LLRF) system that was successfully commissioned during the summer 2021. The new AD LLRF system has routinely captured and decelerated more than 3·107 antiprotons from 3.5 GeV/c to 100 MeV/c in successive steps, referred to as RF segments, interleaved by cooling periods. The LLRF system implements the frequency program from Btrain data received over optical fiber. Beam phase/radial and cavity amplitude/phase feedback loops are operated during each RF segment. An extraction synchronization loop is triggered on the extraction RF segment to transfer a single bunch of antiprotons to ELENA. Extensive diagnostics features are available and operational modes such as bunched beam cooling and bunch rotation have been successfully deployed. The LLRF parameters can be different for each RF segment and are controlled by a dedicated application. This paper gives an overview of the AD LLRF beam commissioning results obtained and challenges overcome. Hints on future steps are also provided.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-TUPOST025  
About • Received ※ 25 May 2022 — Accepted ※ 15 June 2022 — Issue date ※ 17 June 2022  
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOST041 Experience with Computer-Aided Optimizations in LINAC4 and PSB at CERN linac, extraction, cavity, beam-losses 945
 
  • P.K. Skowroński, M.A. Fraser, I. Vojskovic
    CERN, Meyrin, Switzerland
 
  Accelerator optimization is routinely performed with the help of computer algorithms that fully automate these tasks. However, their efficiency, speed, and time to implement varies greatly depending on the algorithms used. In LINAC4 some of the automatic optimization routines were programmed using different algorithms to find the most suitable. We present the problems for which the computer algorithms were used and the results of our comparative study.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-TUPOST041  
About • Received ※ 09 June 2022 — Revised ※ 13 June 2022 — Accepted ※ 22 June 2022 — Issue date ※ 08 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOPT061 Status and Commissioning of the First X-Band RF Source of the TEX Facility klystron, GUI, LLRF, controls 1148
 
  • F. Cardelli, D. Alesini, M. Bellaveglia, S. Bini, M. Ceccarelli, C. Di Giulio, A. Falone, G. Franzini, A. Gallo, L. Piersanti, L. Sabbatini
    INFN/LNF, Frascati, Italy
  • B. Buonomo, G. Catuscelli, R. Ceccarelli, A. Cecchinelli, R. Clementi, E. Di Pasquale, A. Liedl, D. Moriggi, G. Piermarini, S. Pioli, S. Quaglia, L.A. Rossi, M. Scampati, G. Scarselletta, S. Strabioli, S. Tocci, R. Zarlenga
    LNF-INFN, Frascati, Italy
 
  In 2021 started the commissioning of the TEX (Test stand for X-band) facility at the Frascati National laboratories of INFN. This facility has been founded in the framework of the LATINO (Laboratory in Advanced Technologies for INnOvation) project. The current facility layout includes an high power X-band (11.994 GHz) RF source, realized in collaboration with CERN, which will be used for validation and development of the X-band RF high gradient technology in view of the EuPRAXIA@SPARC_LAB project. The RF source is based on a CPI VKX8311 Klystron and a solid state ScandiNova k400 modulator to generate a maximum RF output power of 50 MW at 50 Hz, that will be mainly used for accelerating structure conditioning and waveguide components testing. In this paper the layout, the installation, commissioning and stability measurements of this source are described in detail. The test stand will be soon operative and ready to test the first X-band accelerating structure prototype.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-TUPOPT061  
About • Received ※ 08 June 2022 — Revised ※ 11 June 2022 — Accepted ※ 15 June 2022 — Issue date ※ 10 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOTK033 First RF Measurements of Planar SRF Thin Films with a High Throughput Test Facility at Daresbury Laboratory cavity, SRF, site, pick-up 1283
 
  • D.J. Seal, G. Burt, P. Goudket, O.B. Malyshev, B.S. Sian, R. Valizadeh
    Cockcroft Institute, Warrington, Cheshire, United Kingdom
  • G. Burt, D.J. Seal, B.S. Sian
    Lancaster University, Lancaster, United Kingdom
  • P. Goudket, O.B. Malyshev, R. Valizadeh
    STFC/DL/ASTeC, Daresbury, Warrington, Cheshire, United Kingdom
  • P. Goudket
    ESS, Lund, Sweden
  • H.S. Marks
    Cockcroft Institute, Lancaster University, Lancaster, United Kingdom
 
  The research on superconducting thin films for future radio frequency (RF) cavities requires measuring the RF properties of these films. However, coating and testing thin films on full-sized cavities is both challenging and timeconsuming. As a result, films are typically deposited on small, flat samples and characterised using a test cavity. At Daresbury Laboratory, a facility for testing 10 cm diameter samples has recently been commissioned. The cavity uses RF chokes to allow physical and thermal separation between itself and the sample under test. The facility allows for surface resistance measurements at a resonant frequency of 7.8 GHz, at temperatures down to 4 K, maximum RF power of 1 W and peak magnetic fields of a few mT. The main advantage of this system is the simple sample mounting procedure due to no physical welding between the sample and test cavity. This allows for a fast turnaround time of two to three days between samples. As such, this system can be used to quickly identify which samples are performing well under RF and should require further testing at higher gradient. Details of recent upgrades to this facility, together with measurements of both bulk niobium and thin film samples, will be presented.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-TUPOTK033  
About • Received ※ 08 June 2022 — Revised ※ 12 June 2022 — Accepted ※ 30 June 2022 — Issue date ※ 02 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOTK044 Preliminary Results of a Magnetic and Temperature Map System for 3 GHz Superconducting Radio Frequency Cavities cavity, SRF, radio-frequency, niobium 1315
 
  • I.P. Parajuli, G. Ciovati, J.R. Delayen, A.V. Gurevich, B.D. Khanal
    ODU, Norfolk, Virginia, USA
  • G. Ciovati, J.R. Delayen
    JLab, Newport News, Virginia, USA
 
  Funding: Work supported by NSF Grant 100614-010. Jlab work is supported by Jefferson Science Associates, LLC under U.S. DOE Contract No. DE-AC05-06OR23177.
Superconducting radio frequency (SRF) cavities are fundamental building blocks of modern particle accelerators. A surface resistance in the tens of nanoOhm range is achieved when cooling these cavities to liquid helium temperature, ~2 - 4 K. One of the leading sources of residual losses in SRF cavities is trapped magnetic flux. Flux trapping mechanism depends on different surface preparations and cool-down conditions. We have designed, developed and commissioned a combined magnetic and temperature mapping system using anisotropic magneto-resistance sensors and carbon resistors, respectively, to study the flux trap mechanism in 3 GHz single-cell niobium cavities. In this contribution, we will describe the experimental apparatus and present preliminary test results.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-TUPOTK044  
About • Received ※ 02 June 2022 — Revised ※ 11 June 2022 — Accepted ※ 24 June 2022 — Issue date ※ 25 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOTK045 Magnetic Field Mapping of 1.3 GHz Superconducting Radio Frequency Niobium Cavities cavity, SRF, niobium, radio-frequency 1319
 
  • I.P. Parajuli, G. Ciovati, J.R. Delayen, A.V. Gurevich
    ODU, Norfolk, Virginia, USA
  • G. Ciovati, J.R. Delayen
    JLab, Newport News, Virginia, USA
 
  Funding: Work supported by NSF Grant 100614-010. Jlab work is supported by Jefferson Science Associates, LLC under U.S. DOE Contract No. DE-AC05-06OR23177.
Niobium is the material of choice to build superconducting radio frequency (SRF) cavities, which are fundamental building blocks of modern particle accelerators. These cavities require a cryogenic cool-down to ~2 - 4 K for optimum performance minimizing RF losses on the inner cavity surface. However, temperature-independent residual losses in SRF cavities cannot be prevented entirely. One of the significant contributor to residual losses is trapped magnetic flux. The flux trapping mechanism depends on different factors, such as surface preparations and cool-down conditions. We have developed a diagnostic magnetic field scanning system (MFSS) using Hall probes and anisotropic magneto-resistance sensors to study the spatial distribution of trapped flux in 1.3 GHz single-cell cavities. The first result from this newly commissioned system revealed that the trapped flux on the cavity surface might redistribute with increasing RF power. The MFSS was also able to capture significant magnetic field enhancement at specific cavity locations after a quench.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-TUPOTK045  
About • Received ※ 02 June 2022 — Revised ※ 09 June 2022 — Accepted ※ 20 June 2022 — Issue date ※ 27 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOTK055 One Year of Operation of the New Wideband RF System of the Proton Synchrotron Booster operation, network, cavity, controls 1344
 
  • G.G. Gnemmi, S. Energico, M. Haase, M.M. Paoluzzi, C. Rossi
    CERN, Meyrin, Switzerland
 
  Within the LHC Injectors Upgrade project, the PS Booster(PSB) has been upgraded. Both the injection (160 MeV) and extraction (2 GeV) energies have been increased, bringing also changes in the injection beam revolution frequency, the maximum revolution frequency, and the beam intensity. To meet the requirements of the High Luminosity LHC a new RF system has been designed, based on the wideband frequency characteristics of Finemet® Magnetic Alloy and solid-state amplifiers. The wideband frequency response (1 MHz to 18 MHz) covers all the required frequency schemes in the PSB, allowing multi-harmonics operation. The system is based on a cellular configuration in which each cell provides a fraction of the total RF voltage. The new RF system has been installed in 3 locations replacing the old systems. The installation has been performed during 2019/2020, while the commissioning started later in 2020 and relevant results for the physics have been already observed. This paper describes the new RF chain, the results achieved and the issues that occurred during this year of operation, together with the changes made to the system to improve performance and reliability.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-TUPOTK055  
About • Received ※ 02 June 2022 — Revised ※ 14 June 2022 — Accepted ※ 15 June 2022 — Issue date ※ 28 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOMS002 Status of Sirius Operation storage-ring, cavity, operation, emittance 1385
 
  • L. Liu, M.B. Alves, A.C.S. Oliveira, X.R. Resende, R.M. Seraphim, H. Westfahl Jr., F.H. de Sá
    LNLS, Campinas, Brazil
  • R.H.A. Farias, S.R. Marques
    CNPEM, Campinas, SP, Brazil
 
  SIRIUS is a Synchrotron Light Source Facility based on a 3 GeV electron storage ring with 518 m circumfer-ence and 250 pm.rad emittance. The facility was built and is operated by the Brazilian Synchrotron Light Laboratory (LNLS), located in the CNPEM campus, in Campinas, Brazil. The accelerator commissioning and operation has been split into 2 phases: Phase0, corresponding to the initial accelerator commissioning with 6 beamlines, has been completed, and the project is now in preparation for Phase1, with full accelerator design performance and 14 beamlines in operation. We report on the status of SIRI-US last year operation and ongoing activities towards achieving completion of Phase1.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-TUPOMS002  
About • Received ※ 08 June 2022 — Accepted ※ 17 June 2022 — Issue date ※ 29 June 2022  
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOMS018 Error Analysis and Commissioning Simulation for the PETRA-IV Storage Ring lattice, simulation, optics, storage-ring 1442
 
  • T. Hellert, I.V. Agapov, S.A. Antipov, R. Bartolini, R. Brinkmann, Y.-C. Chae, D. Einfeld, M.A. Jebramcik, J. Keil
    DESY, Hamburg, Germany
 
  The upgrade of the PETRA-III storage ring into a diffraction limited synchrotron radiation source is nearing the end of its detailed technical design phase. We present a preliminary commissioning simulation for PETRA-IV demonstrating that the final corrected machines meet the performance design goals.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-TUPOMS018  
About • Received ※ 10 June 2022 — Revised ※ 10 June 2022 — Accepted ※ 15 June 2022 — Issue date ※ 15 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOMS033 Diamond-II Storage Ring Developments and Performance Studies lattice, injection, storage-ring, impedance 1491
 
  • I.P.S. Martin, H.C. Chao, R.T. Fielder, H. Ghasem, J. Kallestrup, T. Olsson, B. Singh, S.W. Wang
    DLS, Oxfordshire, United Kingdom
 
  The Diamond-II project includes a replacement of the existing double-bend achromat storage ring with a modified hybrid 6-bend achromat, doubling the number of straight sections and increasing the photon beam brightness by up to two orders of magnitude*. The design and performance characterisation of the new storage ring has continued to progress, including a switch to an aperture-sharing injection scheme, freezing the magnet layout, studying the impact of IDs, developing a commissioning procedure and investigating collective effects. In this paper we present an overview of these studies, including final performance estimates.
*Diamond-II Technical Design Report, Diamond Light Source Ltd.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-TUPOMS033  
About • Received ※ 07 June 2022 — Revised ※ 13 June 2022 — Accepted ※ 24 June 2022 — Issue date ※ 27 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOMS052 Considerations From Deploying, Commissioning, and Maintaining the Control System for LCLS-II Undulators undulator, controls, EPICS, vacuum 1546
 
  • M.A. Montironi, C.J. Andrews, G. Marcus, H.-D. Nuhn
    SLAC, Menlo Park, California, USA
 
  Funding: This work was supported by Department of Energy, Office of Basic Energy Sciences, contract DE-AC02-76SF00515
Two new undulator lines have been installed as part of the Linac Coherent Light Source upgrade (LCLSII) at SLAC National Accelerator Laboratory. One undulator line, composed of 21 horizontally polarizing undulator segments, is dedicated to producing Soft X-Rays (SXR). The other line, composed of 32 vertically polarizing undulator segments, is dedicated to producing Hard X-Rays (HXR). The devices were installed, and the control system was deployed in 2019. Commissioning culminated with the achievement of first light from the HXR undulator in the Summer of 2020 and from the SXR undulator in the Fall of 2020. Since then, both undulator lines have been successfully providing x-Rays to user experiments with very limited downtime. In this paper, we first describe the strategies utilized to simplify the deployment, commissioning, and maintenance of the control system. Such strategies include scripts for automated components calibration and monitoring, a modular software structure, and debugging manuals for accelerator operators. Then, we discuss lessons learned which could be applicable to similar projects in the future.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-TUPOMS052  
About • Received ※ 08 June 2022 — Revised ※ 10 June 2022 — Accepted ※ 16 June 2022 — Issue date ※ 26 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEIYGD1 Achievements and Performance Prospects of the Upgraded LHC Injectors injection, brightness, proton, kicker 1610
 
  • V. Kain, S.C.P. Albright, R. Alemany-Fernández, M.E. Angoletta, F. Antoniou, T. Argyropoulos, F. Asvesta, B. Balhan, M.J. Barnes, D. Barrientos, H. Bartosik, P. Baudrenghien, G. Bellodi, N. Biancacci, A. Boccardi, J.C.C.M. Borburgh, C. Bracco, E. Carlier, D.G. Cotte, J. Coupard, H. Damerau, G.P. Di Giovanni, A. Findlay, M.A. Fraser, A. Funken, B. Goddard, G. Hagmann, K. Hanke, A. Huschauer, M. Jaussi, I. Karpov, T. Koevener, D. Küchler, J.-B. Lallement, A. Lasheen, T.E. Levens, K.S.B. Li, A.M. Lombardi, N. Madysa, E. Mahner, M. Meddahi, L. Mether, B. Mikulec, J.C. Molendijk, E. Montesinos, D. Nisbet, F.-X. Nuiry, G. Papotti, K. Paraschou, F. Pedrosa, T. Prebibaj, S. Prodon, D. Quartullo, E. Renner, F. Roncarolo, G. Rumolo, B. Salvant, M. Schenk, R. Scrivens, E.N. Shaposhnikova, P.K. Skowroński, A. Spierer, F. Tecker, D. Valuch, F.M. Velotti, R. Wegner, C. Zannini
    CERN, Meyrin, Switzerland
 
  To provide HL-LHC performance, the CERN LHC injector chain underwent a major upgrade during an almost 2-year-long shutdown. In the first half of 2021 the injectors were gradually re-started with the aim to reach at least pre-shutdown parameters for LHC as well as for fixed target beams. The strategy of the commissioning across the complex, a summary of the many challenges and finally the achievements will be presented. Several lessons were learned and have been integrated to define the strategy for the performance ramp-up over the coming years. Remaining limitations and prospects for LHC beam parameters at the exit of the LHC injector chain in the years to come will be discussed. Finally, the emerging need for improved operability of the CERN complex will be addressed, with a description of the first efforts to meet the availability and flexibility requirements of the HL-LHC era while at the same time maximizing fixed target physics output.  
slides icon Slides WEIYGD1 [5.905 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-WEIYGD1  
About • Received ※ 08 June 2022 — Accepted ※ 15 June 2022 — Issue date ※ 09 July 2022  
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEINGD1 Industry and Accelerator Science, Technology, and Engineering - the Need to Integrate (Building Bridges) electron, laser, radiation, network 1644
 
  • R. Geometrante
    KYMA, Trieste, Italy
  • S. Biedron
    Element Aero, Chicago, USA
  • E. Braidotti
    CAEN ELS srl, Trieste, Italy
  • J.M.A. Priem
    VDL ETG, Eindhoven, The Netherlands
  • J.C. Rugsancharoenphol
    FTI, Bangkok, Thailand
  • S.L. Sheehy
    The University of Melbourne, Melbourne, Victoria, Australia
  • M. Vretenar
    CERN, Meyrin, Switzerland
 
  Abstract  
slides icon Slides WEINGD1 [36.079 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-WEINGD1  
About • Received ※ 05 July 2022 — Accepted ※ 04 July 2022 — Issue date ※ 05 July 2022  
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPOST008 Optics Correction Strategy for Run 3 of the LHC optics, coupling, injection, quadrupole 1687
 
  • T.H.B. Persson, F.S. Carlier, A. Costa Ojeda, J. Dilly, V. Ferrentino, E. Fol, H. García Morales, M. Hofer, E.J. Høydalsvik, J. Keintzel, M. Le Garrec, E.H. Maclean, L. Malina, F. Soubelet, R. Tomás García, A. Wegscheider, L. van Riesen-Haupt
    CERN, Meyrin, Switzerland
  • J.F. Cardona
    UNAL, Bogota D.C, Colombia
 
  After almost 4 years of shutdown the LHC is again operational in 2022. Experience from the previous Long Shutdown (LS) has shown that the local errors around the triplet magnets changed significantly and it is likely we will again see different errors in 2022. In the LHC there is an interplay between the linear and the nonlinear correction which can make the corrections difficult and time-consuming to find. In this article, we describe the measurements and corrections performed during the commissioning in 2022 in order to control both the linear and the nonlinear optics to high precision.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-WEPOST008  
About • Received ※ 08 June 2022 — Revised ※ 25 June 2022 — Accepted ※ 04 July 2022 — Issue date ※ 10 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPOST025 A High Power Prototype of a Harmonic Kicker Cavity kicker, cavity, operation, electron 1749
 
  • G.-T. Park, G.A. Grose, J. Guo, A. OBrien, R.A. Rimmer, H. Wang, R.S. Williams
    JLab, Newport News, Virginia, USA
  • S.A. Overstreet
    ODU, Norfolk, Virginia, USA
 
  A harmonic kicker, a beam exchange device that can deflect the beam at an ultra-fast time scale (a few ns), has been developed in Jefferson Lab *, **. The high power prototype that can deliver more than a 100 kV kick at 7 kW was fabricated. The RF performance of cavity such as the harmonic resonant frequencies, kick profiles, it’s stability, and electric center is tested at bench. The cavity will eventually be tested with a beam at Upgraded Injector Test Facility (UITF) in Jefferson Lab. In this paper, we report some features of fabrication and bench test results. We also briefly describe our beam test plan in the future.
* G.Park, H.Wang, R.A.Rimmer, S. Wang, and J.Guo, THP092, Proceedings of IPAC2018, Vancouver, Canada (2018).
** G.Park, et al, WEPRBO99, Proceedings of IPAC2019, Melbourne, Australia (2019).
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-WEPOST025  
About • Received ※ 11 June 2022 — Revised ※ 15 June 2022 — Accepted ※ 16 June 2022 — Issue date ※ 20 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPOPT007 First Interaction Region Local Coupling Corrections in the LHC Run 3 coupling, optics, quadrupole, experiment 1838
 
  • F. Soubelet, T.H.B. Persson, R. Tomás García
    CERN, Meyrin, Switzerland
  • Ö. Apsimon, C.P. Welsch
    Cockcroft Institute, Warrington, Cheshire, United Kingdom
 
  Funding: This research is supported by the LIV. DAT Center for Doctoral Training, STFC and the European Organization for Nuclear Research
The successful operation of large scale particle accelerators depends on the precise correction of unavoidable magnetic field or magnet alignment errors present in the machine. During the LHC Run 2, local linear coupling in the interaction regions (IR) was shown to have a significant impact on the beam size, making its proper handling a necessity for Run 3 and the High Luminosity LHC (HL-LHC). A new approach to accurately minimise the local IR linear coupling based on correlated external variables such as the |C-| had been proposed, which relies on the application of a rigid waist shift in order to create an asymmetry in the IR optics. In this contribution, preliminary corrections from the 2021 beam test and the early 2022 commissioning are presented, as well as first results of the new method’s experimental configuration tests in the LHC Run 3 commissioning.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-WEPOPT007  
About • Received ※ 03 June 2022 — Revised ※ 15 June 2022 — Accepted ※ 16 June 2022 — Issue date ※ 19 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPOPT021 A Discharge Plasma Source Development Platform for Accelerators: The ADVANCE Lab at DESY plasma, diagnostics, laser, GUI 1886
 
  • J.M. Garland, R.T.P. D’Arcy, M. Dinter, S. Karstensen, S. Kottler, G. Loisch, K. Ludwig, J. Osterhoff, A. Rahali, A. Schleiermacher, S. Wesch
    DESY, Hamburg, Germany
 
  Novel plasma-based accelerators, as well as advanced, high-gradient beam-manipulation techniques’for example passive or active plasma lenses’require reliable and well-characterized plasma sources, each optimized for their individual task. A very efficient and proven way of producing plasmas for these applications is by directly discharging an electrical current through a confined gas volume. To host the development of such discharge-based plasma sources for advanced accelerators, the ATHENA Discharge deVelopment ANd Characterization Experiment (ADVANCE) laboratory has been established at DESY. In this contribution we introduce the laboratory, give a summary of available infrastructure and diagnostics, as well as a brief overview of current and planned scientific goals.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-WEPOPT021  
About • Received ※ 08 June 2022 — Revised ※ 16 June 2022 — Accepted ※ 17 June 2022 — Issue date ※ 09 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPOPT060 Controlling Landau Damping via Feed-Down From High-Order Correctors in the LHC and HL-LHC optics, target, simulation, controls 1995
 
  • J. Dilly, E.H. Maclean, R. Tomás García
    CERN, Meyrin, Switzerland
 
  Funding: This work has been supported by the HiLumi Project and been sponsored by the Wolfgang Gentner Programme of the German Federal Ministry of Education and Re-search.
Amplitude detuning measurements in the LHC have shown that a significant amount of detuning is generated in Beam 1 via feed-down from decapole and dodecapole field errors in the triplets of the experiment insertion regions, while in Beam 2 this detuning is negligible. In this study, we investigate the cause of this behavior and we attempt to find corrections that use the feed-down from the nonlinear correctors in the insertion region for amplitude detuning.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-WEPOPT060  
About • Received ※ 07 June 2022 — Revised ※ 15 June 2022 — Accepted ※ 16 June 2022 — Issue date ※ 06 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPOTK001 Status of the Normal Conducting Linac at the European Spallation Source DTL, rfq, LEBT, MEBT 2019
 
  • D.C. Plostinar, C. Amstutz, S. Armanet, R.A. Baron, E.C. Bergman, A.K. Bhattacharyya, B.E. Bolling, W. Borg, S. Calic, M. Carroll, J. Cereijo García, J. Christensson, J.D. Christie, H. Danared, C.S. Derrez, E.M. Donegani, S. Ekström, M. Eriksson, M. Eshraqi, J.F. Esteban Müller, K. Falkland, M.J. Ferreira, A. Forsat, S. Gabourin, A.A. Gorzawski, V. Grishin, P.O. Gustavsson, S. Haghtalab, V.A. Harahap, H. Hassanzadegan, W. Hees, J.J. Jamróz, A. Jansson, M. Jensen, B. Jones, M. Kalafatic, I. Kittelmann, H. Kocevar, S. Kövecses de Carvalho, E. Laface, B. Lagoguez, Y. Levinsen, M. Lindroos, A. Lundmark, M. Mansouri, C. Marrelli, C.A. Martins, J.P.S. Martins, S. Micic, N. Milas, R. Miyamoto, M. Mohammednezhad, R. Montaño, M. Muñoz, G. Mörk, D.J.P. Nicosia, B. Nilsson, D. Noll, A. Nordt, T. Olsson, L. Page, D. Paulic, S. Pavinato, S. Payandeh Azad, A. Petrushenko, J. Riegert, A. Rizzo, K.E. Rosengren, K. Rosquist, M. Serluca, T.J. Shea, A. Simelio, S. Slettebak, A.G. Sosa, H. Spoelstra, A.M. Svensson, L. Svensson, R. Tarkeshian, L. Tchelidze, C.A. Thomas, E. Trachanas, K. Vestin, R. Zeng, P.L. van Velze, N. Öst
    ESS, Lund, Sweden
  • L. Antoniazzi, C. Baltador, L. Bellan, M. Comunian, E. Fagotti, L. Ferrari, M.G. Giacchini, F. Grespan, M. Montis, A. Palmieri, A. Pisent, D. Scarpa
    INFN/LNL, Legnaro (PD), Italy
  • T. Bencivenga, P. Mereu, C. Mingioni, M. Nenni, E. Nicoletti
    INFN-Torino, Torino, Italy
  • I. Bustinduy, A. Conde, D. Fernández-Cañoto, N. Garmendia, P.J. González, G. Harper, A. Kaftoosian, J. Martin, I. Mazkiaran, J.L. Muñoz, A.R. Páramo, S. Varnasseri, A.Z. Zugazaga
    ESS Bilbao, Zamudio, Spain
  • A.C. Chauveau, P. Hamel, O. Piquet
    CEA-IRFU, Gif-sur-Yvette, France
  • L. Neri
    INFN/LNS, Catania, Italy
 
  The construction of the ESS accelerator is in full swing. Many key components have been delivered from our in-kind partners and installation, testing and commissioning is making remarkable progress. The first machine section to be commissioned with beam is the Normal Conducting Linac (NCL). When completed, a 14 Hz, 2.86 ms proton beam up to 62.5 mA will be transported from the Ion Source, through the Low Energy Beam Transport (LEBT) line, the Radiofrequency Quadrupole (RFQ), the Medium Energy Beam Transport (MEBT) line and the five Drift Tube Linac (DTL) tanks up to 90 MeV where it will be injected in the first superconducting module of the machine. This paper will highlight recent progress across the NCL, present briefly the first commissioning results and discuss the upcoming phases as well as challenges in delivering a machine capable of meeting the requirements for a next generation spallation neutron facility.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-WEPOTK001  
About • Received ※ 13 June 2022 — Accepted ※ 15 June 2022 — Issue date ※ 02 July 2022  
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPOTK009 Processes and Tools to Manage CERN Programmed Stops Applied to the Second Long Shutdown of the Accelerator Complex database, proton, operation, synchrotron 2048
 
  • E. Vergara Fernandez, A. Ansel, M. Barberan Marin, M. Bernardini, S. Chemli, J. Coupard, K. Foraz, D. Hay, J.M. Jimenez, D.J. Mcfarlane, F. Pedrosa, M. Pirozzi, J.Ph.G.L. Tock
    CERN, Meyrin, Switzerland
 
  The preparation and follow-up of CERN accelerator complex programmed stops require clear processes and methodologies. The LHC and its Injectors were stopped in December 2018, to maintain, consolidate and upgrade the different equipment of the accelerator chain. During the Long Shutdown 2 (LS2), major projects were implemented such as the LHC Injectors upgrade and the LHC Dipoles Diodes consolidation. The installation of some equipment of the HL-LHC project took also place. This paper presents the application to the LS2 of the processes and tools to managed CERN programmed stops: it covers the preparation, implementation and follow up phases, as well as the KPIs, the tools used to build a coherent schedule and to follow up and report the progress. The description of the methodology to create a linear schedule, as well the construction of automatised broken lines and progress curves are detailed. It also describes the organizational set-up for the coordination of the works, the main activities and the key milestones. The impact of the COVID-19 on the long shutdown will be described, especially the strategy implemented to minimise its consequences.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-WEPOTK009  
About • Received ※ 07 June 2022 — Revised ※ 10 June 2022 — Accepted ※ 13 June 2022 — Issue date ※ 17 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPOTK012 Commissioning the New LLRF System of the CERN PS Booster cavity, operation, injection, LLRF 2060
 
  • S.C.P. Albright, M.E. Angoletta, D. Barrientos, A. Findlay, M. Jaussi, J.C. Molendijk
    CERN, Meyrin, Switzerland
 
  The PS Booster (PSB) is the first synchrotron in the injection chain for protons. The beams produced for the LHC and various fixed target experiments cover a very large parameter space. Over the Long Shutdown 2 (LS2), the PSB was heavily upgraded as part of the LHC Injectors Upgrade (LIU) project. The low-level RF systems now drive the new Finemet-loaded cavities, control RF synchronisation for the new injection mechanism, and cope with the increased injection and extraction energies. The Finemet cavities provide exceptional flexibility, allowing an arbitrary distribution of voltage at different revolution frequency harmonics, but at the cost of significant broadband impedance. The new injection mechanism allows bunch-to-bucket multi-turn injection, which significantly reduces the amount of beam loss at the start of the cycle. The longitudinal beam production schema for each beam-type was developed based on simulations during LS2, and then adapted during the setting-up phase to suit the final operational configuration. This paper discusses the commissioning of the new LLRF, and the consequences of the LIU upgrades on the production of various beams.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-WEPOTK012  
About • Received ※ 25 May 2022 — Revised ※ 15 June 2022 — Accepted ※ 16 June 2022 — Issue date ※ 07 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THOXGD1 ELENA - From Commissioning to Operation proton, antiproton, experiment, operation 2391
 
  • L. Ponce, L. Bojtár, C. Carli, B. Dupuy, Y. Dutheil, P. Freyermuth, D. Gamba, L.V. Jørgensen, B. Lefort, S. Pasinelli
    CERN, Meyrin, Switzerland
 
  In 2021 the Extra Low ENergy Antiproton ring (ELENA) moved from commissioning into the physics production phase providing 100 keV antiprotons to the newly connected experiments paving the way to an improved trapping efficiency by one to two orders of magnitude compared to the AD era. After recalling the major work undertaken during the CERN Long Shutdown 2 (2019-2020) in the antiproton deceleration complex, details will be given on the ELENA ring and the new electrostatic transfer line beam commissioning using an ion source. Sub-sequentially, the progress from commissioning with ions to operation with antiprotons will be described with emphasis on the achieved beam performance. Finally, the impact on the performance of the main hardware systems will be reviewed.  
slides icon Slides THOXGD1 [9.720 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-THOXGD1  
About • Received ※ 07 June 2022 — Revised ※ 15 June 2022 — Accepted ※ 15 June 2022 — Issue date ※ 01 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THOXGD3 Commissioning Status of the RAON Superconducting Accelerator cryomodule, linac, quadrupole, rfq 2399
 
  • H.J. Kim, Y.J. Choi, Y.S. Chung, J. Heo, I.S. Hong, J.-H. Jang, D. Jeon, H. Jin, G.D. Kim, Y.H. Kim, J.W. Kwon, S. Lee, B.-S. Park, M.J. Park, C.W. Son
    IBS, Daejeon, Republic of Korea
  • D.M. Kim
    KUS, Sejong, Republic of Korea
  • E.H. Lim
    Korea University Sejong Campus, Sejong, Republic of Korea
  • S.H. Moon
    UNIST, Ulsan, Republic of Korea
 
  The Rare isotope Accelerator Complex for ON-line experiments (RAON) has been proposed as a multi-purpose accelerator facility for providing beams of exotic rare isotopes of various energies. It can deliver ions from hydrogen (proton) to uranium. Protons and uranium ions are accelerated up to 600 MeV and 200 MeV/u respectively. It can provide various rare isotope beams which are produced by isotope separator on-line system. The RAON injector was successfully commissioned in 2021 to study the initial beam parameters from the main technical systems, such as the ECR ion source and RFQ, and to find the optimized LEBT and MEBT setpoints and matching conditions. In this paper, we present the current commissioning status of the RAON injector in preparation for the upcoming SCL3 beam commissioning.  
slides icon Slides THOXGD3 [6.508 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-THOXGD3  
About • Received ※ 08 June 2022 — Revised ※ 12 June 2022 — Accepted ※ 14 June 2022 — Issue date ※ 15 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THPOST016 Development Progress of HEPS LINAC linac, emittance, simulation, LLRF 2472
 
  • C. Meng, N. Gan, D.Y. He, X. He, Y. Jiao, J.Y. Li, J.D. Liu, Y.M. Peng, H. Shi, G. Shu, S.C. Wang, O. Xiao, J.R. Zhang, Z.D. Zhang, Z.S. Zhou
    IHEP, Beijing, People’s Republic of China
  • X.H. Lu, X.J. Nie
    IHEP CSNS, Guangdong Province, People’s Republic of China
 
  The High Energy Photon Source (HEPS) is a synchrotron radiation source of ultrahigh brightness and under construction in China. Its accelerator system is comprised of a 6-GeV storage ring, a full energy booster, a 500-MeV Linac and three transfer lines. The Linac is a S-band normal conducting electron linear accelerator with available bunch charge up to 10 nC. The Linac installation has been finished at the end of May this year. The system joint debugging and device conditioning of the accelerating units, the power supplies, et al., are in progress. The beam commissioning will start in September 2022. This paper presents the status of the HEPS Linac and detailed introduction of the beam commissioning simulations and preparations.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-THPOST016  
About • Received ※ 08 June 2022 — Revised ※ 10 June 2022 — Accepted ※ 16 June 2022 — Issue date ※ 09 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THPOST039 SPS Beam Dump System (SBDS) Commissioning After Relocation and Upgrade kicker, controls, vacuum, hardware 2530
 
  • P. Van Trappen, E. Carlier, L. Ducimetière, V. Namora, V. Senaj, F.M. Velotti, N. Voumard
    CERN, Meyrin, Switzerland
 
  In order to overcome several machine limitations, the SBDS has been relocated from LSS1 (Long Straight Section 1) to LSS5 during LS2 (Long Shutdown 2) with an important upgrade of the extraction kicker installation. An additional vertical deflection kicker magnet (MKDV) was produced and installed while the high voltage (HV) pulse generators have been upgraded by changing gas-discharge switches (thyratrons and ignitrons) to semiconductor stacks operating in oil. Furthermore the horizontal sweep generators have been upgraded to allow for a lower kick strengths. The controls, previously consolidated during LS1, went through an additional light consolidation phase with among others the upgrade of the trigger & retrigger distribution system and the installation of a new fast-interlocks detection system. This paper describes the commissioning without and with beam and elaborates on the measured improvements and encountered problems with corrective mitigations.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-THPOST039  
About • Received ※ 07 June 2022 — Accepted ※ 12 June 2022 — Issue date ※ 15 June 2022  
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THPOPT016 Commissioning Simulations for the DIAMOND-II Upgrade injection, optics, storage-ring, quadrupole 2598
 
  • H.C. Chao, R.T. Fielder, J. Kallestrup, I.P.S. Martin, B. Singh
    DLS, Oxfordshire, United Kingdom
 
  The Diamond-II storage ring, compared to Diamond, improves the natural beam emittance from 2.7 nm to 160 pm and the beam energy from 3 to 3.5 GeV. The number of straight sections is also doubled from 24 to 48 thanks to the modified hybrid six-bend-achromat lattice. To reduce the impact on the existing science program, the dark time period must be minimised. To assist in this aim, storage ring commissioning simulations have been carried out to predict and resolve possible issues. These studies include beam commissioning starting from on-axis first-turn beam threading up to beam based alignment and full linear optics correction with stored beam. The linear optics corrections with insertion devices are also included. The machine characterisations at different stages are compared. Considerations on realistic chamber limitations, error definitions and some commissioning strategies are also discussed.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-THPOPT016  
About • Received ※ 19 May 2022 — Accepted ※ 15 June 2022 — Issue date ※ 15 June 2022  
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THPOPT039 Performance Report of the SOLEIL Multipole Injection Kicker injection, kicker, storage-ring, synchrotron 2675
 
  • R. Ollier, P. Alexandre, R. Ben El Fekih, A. Gamelin, N. Hubert, M. Labat, A. Nadji, L.S. Nadolski, M.-A. Tordeux
    SOLEIL, Gif-sur-Yvette, France
 
  A Multipole Injection Kicker (MIK) was installed in a short straight section of the SOLEIL storage ring and successfully commissioned in 2021. A small horizontal orbit distortion in the micrometer range was achieved outperforming the standard bump-based injection scheme installed in a 12-m long straight section. Refined studies have been conducted to fully understand and further improve the performance of the device. Indeed, a novel generation of the MIK will be the key element for the injection scheme of the SOLEIL Upgrade. We report simulation studies and the latest MIK experimental performance. Both injected and stored beam-based measurements were performed using new types of diagnostics with turn-by-turn capability (Libera Brillance+ BPM, KALYPSO: 2x1D imaging). The residual perturbations on the beam positions and sizes were measured; the magnetic field of the MIK device was reconstructed. An unexpected kick was detected in the vertical plane and an active correction implemented to cancel the resulting perturbation.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-THPOPT039  
About • Received ※ 09 June 2022 — Accepted ※ 29 June 2022 — Issue date ※ 06 July 2022  
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THPOPT044 The Alkali-Metal Photocathode Preparation Facility at Daresbury Laboratory: First Caesium Telluride Deposition Results cathode, electron, emittance, FEL 2693
 
  • H.M. Churn, C. Benjamin, L.B. Jones, T.C.Q. Noakes
    STFC/DL/ASTeC, Daresbury, Warrington, Cheshire, United Kingdom
  • C. Benjamin
    University of Warwick, Coventry, United Kingdom
  • H.M. Churn, L.B. Jones, T.C.Q. Noakes
    Cockcroft Institute, Warrington, Cheshire, United Kingdom
 
  Fourth generation light sources require high brightness electron beams. To achieve this a photocathode with a high quantum efficiency and low intrinsic emittance is required, which is also robust with a long operational lifetime and low dark current. Alkali-metal photocathodes have the potential to fulfil these requirements, so are an important research area for the accelerator physics community. STFC Daresbury Laboratory are currently commissioning the Alkali-metal Photocathode Preparation Facility (APPF) which will be used to grow alkali photocathodes. Photocathodes produced by the APPF will be analysed using Daresbury Laboratory’s existing Multiprobe system* and the Transverse Energy Spread Spectrometer (TESS)**. Multiprobe can perform a variety of surface analysis techniques while the TESS can measure the Mean Transverse Energy of a photocathode from its Transverse Energy Distribution Curve over a large range of illumination wavelengths. We present an overview on our current progress in the commissioning and testing of the APPF, the results from the first Cs-Te deposition and detail the work planned to facilitate the manufacture of Cs2Te photocathodes for the CLARA accelerator***.
*B.L. Militsyn, 4th EuCARD2 WP12.5 meeting, Warsaw, 14-15 Mar. 2017
**L. Jones et al., Proc. FEL ’13, TUPPS033, 290-293
***D. Angal-Kalinin et al., Phys. Rev. Accel. Beams, Vol. 23, Iss. 4, 2020
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-THPOPT044  
About • Received ※ 07 June 2022 — Revised ※ 10 June 2022 — Accepted ※ 13 June 2022 — Issue date ※ 23 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THPOPT060 Tolerance Study on the Geometrical Errors for a Planar Superconducting Undulator undulator, FEL, simulation, FEM 2734
 
  • V. Grattoni, S. Casalbuoni, B. Marchetti
    EuXFEL, Schenefeld, Germany
 
  At the European XFEL, a superconducting afterburner is considered for the SASE2 hard X-ray beamline. It will consist of six undulator modules. Within each module, two superconducting undulators (SCU) 2 m long are present. Such an afterburner will enable photon energies above 30 keV. A high field quality of the SCU is crucial to guarantee the quality of the electron beam trajectory, which is directly related to the spectral quality of the emitted free-electron laser (FEL) radiation. Therefore, the effects of the SCU’s mechanical imperfections on the resultant magnetic field have to be carefully characterized. In this contribution, we present possible mechanical errors affecting the undulator structure, and we perform an analytical study aimed at determining the tolerances on these errors for our SCUs.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-THPOPT060  
About • Received ※ 03 June 2022 — Revised ※ 10 June 2022 — Accepted ※ 14 June 2022 — Issue date ※ 27 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THPOTK020 Recent Experience from the Large-Scale Deployment of Power Converters with Magnet Energy Recovery operation, controls, quadrupole, experiment 2809
 
  • K.D. Papastergiou, G. Le Godec, V. Montabonnet
    CERN, Meyrin, Switzerland
 
  A new powering solution was deployed at CERN for transfer lines in the injector complex as part of the LHC injectors upgrade. The new powering uses regenerative power converters to recycle the magnet energy between physics operations. This work gives an overview of the developed technology, the way it is used in the accelerators complex and some results of first period of operation with beam.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-THPOTK020  
About • Received ※ 03 June 2022 — Revised ※ 11 June 2022 — Accepted ※ 25 June 2022 — Issue date ※ 28 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THPOTK034 Vacuum System Performance of the 3 GeV Electron Storage Ring at MAX IV Laboratory vacuum, storage-ring, operation, injection 2836
 
  • M.J. Grabski, E. Al-Dmour, S.M. Scolari
    MAX IV Laboratory, Lund University, Lund, Sweden
 
  The 3 GeV electron storage ring at MAX IV laboratory is the first synchrotron light source with compact multi-bend achromat (MBA) magnet lattice to achieve ultra-low emittance. The vacuum system of the accelerator is fully coated with non-evaporable getter (NEG) thin film to ensure low gas density. The storage ring started commissioning in August 2015 and currently delivers photon beams from insertion devices (IDs) to 9 beamlines that are in user operation or commissioning. After over 6 years of operation, the NEG coated vacuum system continues to be reliable, is conditioning well and do not pose any limitation to the accelerator operation. The average dynamic pressure is lower than the design value (below 3·10-10 mbar) and is reducing with the accumulated beam dose. The vacuum beam lifetime is greater than 39 Ah, and the total beam lifetime is above the design value of 5 Ah - thus is not limited by the residual gas density. Several successful interventions to install new vacuum components were performed on few achromats in the storage ring during shutdowns. Some of them were done utilizing purified neon gas to vent the vacuum system, thus avoiding the need of re-activation of the NEG coating and saving intervention time without compromising the storage ring performance.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-THPOTK034  
About • Received ※ 08 June 2022 — Revised ※ 12 June 2022 — Accepted ※ 14 June 2022 — Issue date ※ 28 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THPOTK058 CERN’s East Experimental Area: A New Modern Physics Facility experiment, target, operation, secondary-beams 2911
 
  • S. Evrard, D. Banerjee, J. Bernhard, F. Carvalho, S. Danzeca, M. Lazzaroni, B. Rae, G. Romagnoli
    CERN, Meyrin, Switzerland
 
  CERN’s East Area has hosted a variety of fixed-target experiments since the 1950s, using four beamlines from the Proton Synchrotron (PS). Over the past 4 years, the experimental area - CERN’s second largest - has undergone a complete makeover. New instrumentation and beamline configuration have improved the precision of data collection, and new magnets and power convertors have drastically reduced the area’s energy consumption. This article will summarize the major challenges encountered for the design of the renovated beamlines and for the preparation and test of the components. The infrastructure was carefully fitted resulting in a very smooth beam commissioning, the details of which will also be presented along with the restart of physics in the second half of 2021. With the return of the beams in the accelerator complex, the East Area’s experiments have taken physics measurements again and the facility’s central role in the modern physics landscape has been restored.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-THPOTK058  
About • Received ※ 08 June 2022 — Revised ※ 12 June 2022 — Accepted ※ 14 June 2022 — Issue date ※ 05 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THPOTK059 Laser System for SuperKEKB RF Gun in Phase III Commissioning laser, electron, injection, gun 2914
 
  • R. Zhang, M. Yoshida, X. Zhou
    KEK, Ibaraki, Japan
  • H.K. Kumano, N. Toyotomi
    Mitsubishi Electric System & Service Co., Ltd, Tsukuba, Japan
 
  In order to generate high quality electron beam with high charge in Phase III commissioning of SuperKEKB, some improvements have been done in Ytterbium doped fiber and Neodymium doped YAG (Nd:YAG) hybrid laser system. Spatial reshaping part for the 4th harmonic laser beam at 266 nm has been adopted to realize low emittance electron beam. In addition, for achieving continuous and stable laser operation, position feedback system has also been used to improve the pointing stability of laser beam. In 2021 commissioning of SuperKEKB, stable 2 nC electron beam is generated for high energy ring (HER) injection. Meanwhile, we achieved the best emittance results at B-sector of linac injector and BT line for comparable low injection background and higher injection efficiency. With the aim of generating higher charge electron beam with good quality in the following commissioning, a perspective towards the next step update for current laser system is also introduced.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-THPOTK059  
About • Received ※ 08 June 2022 — Revised ※ 12 June 2022 — Accepted ※ 14 June 2022 — Issue date ※ 04 July 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THPOMS002 Gantry Beamline and Rotator Commissioning at the Medaustron Ion Therapy Center proton, optics, quadrupole, radiation 2933
 
  • M.T.F. Pivi, L. Adler, G. Guidoboni, G. Kowarik, C. Kurfürst, C. Maderböck, D.A. Prokopovich, I. Strašík
    EBG MedAustron, Wr. Neustadt, Austria
  • G. Kowarik
    GKMT Consulting, Consulting and Project Management, Vienna, Austria
  • M. Pavlovič
    STU, Bratislava, Slovak Republic
  • M.G. Pullia
    CNAO Foundation, Pavia, Italy
  • V. Rizzoglio
    PSI, Villigen PSI, Switzerland
 
  The MedAustron Particle Therapy Accelerator located in Austria, delivers proton beams in the energy range 60-250 MeV/n and carbon ions 120-400 MeV/n for medical treatment in two irradiation rooms, clinically used for tumor therapy. Proton beams up to 800 MeV/n are also provided to a room dedicated to scientific research. Over the last two years, in parallel to clinical operations, we have completed the installation and commissioning of the gantry beam line in a dedicated room, ready for the first patient treatment in early 2022. In this manuscript, we provide an overview of the MedAustron gantry beam commissioning including the world-wide first ’rotator’ system, a rotating beamline located upstream of the gantry and used to match the slowly extracted non-symmetric beams into the coordinate system of the gantry. Using the rotator, all beam parameters at the location of the patient become independent of the gantry rotation angle. Furthermore, both the gantry and the high energy transfer line optics had to be redesigned and adapted to the rotator-mode of operation. A review of the beam commissioning including technical solutions, main results and reference measurements is presented.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-THPOMS002  
About • Received ※ 08 June 2022 — Accepted ※ 16 June 2022 — Issue date ※ 04 July 2022  
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)