MOOPLGD2 |
SPS-II: A 4th Generation Synchrotron Light Source in Southeast Asia |
764 |
|
- P. Klysubun, S. Boonsuya, T. Chanwattana, S. Jummunt, N. Juntong, A. Kwankasem, T. Phimsen, P. Photongkam, S. Prawanta, T. Pulampong, K. Sittisard, S. Srichan, P. Sudmuang, P. Sunwong, O. Utke
SLRI, Nakhon-Ratchasima, Thailand
|
|
|
Upon its completion, Siam Photon Source II (SPS-II) will be the first 4th generation synchrotron light source in Southeast Asia. The 3.0 GeV, 327.5 m storage ring based on the Double-Triple Bend Achromat lattice will have the natural emittance of 0.97 nm·rad. The storage ring includes 14 long and 14 short straight sections for insertion devices and machine subsys-tems. The beam injection will be performed by a 150 MeV linear accelerator and a full-energy concentric booster synchrotron sharing the same tunnel with the storage ring. In the first phase, there will be 7 insertion devices and 7 associated beamlines with the end sta-tions for different techniques utilizing synchrotron radiation from 80 eV to 60 keV. High-energy and high-brightness radiation generated by the new light source will serve as one of the most powerful analytical tools in the region for advanced science and technology research.
|
|
|
Slides MOOPLGD2 [4.168 MB]
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-IPAC2022-MOOPLGD2
|
|
About • |
Received ※ 12 June 2022 — Accepted ※ 04 July 2022 — Issue date ※ 05 July 2022 |
|
Cite • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|
THPOST041 |
Construction and Manufacturing Process of Siam Photon Source II Storage Ring Girder Prototype |
2537 |
|
- S. Srichan, S. Klinkhieo, M. Phanak, S. Prabngulueam, P. Pruekthaisong, K. Sittisard
SLRI, Nakhon Ratchasima, Thailand
- O. Utke
Synchrotron Light Research Institute (SLRI), Muang District, Thailand
|
|
|
The Siam Photon Source II storage ring is designed with low emittance. This new machine requires a high performance support system and a precise alignment capability. In order to meet these requirements, we have planned for construction of a half-cell component prototype. In the end of 2021, we completed the first girder prototype. This report will describe construction and manufacturing process.
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-IPAC2022-THPOST041
|
|
About • |
Received ※ 08 June 2022 — Revised ※ 15 June 2022 — Accepted ※ 16 June 2022 — Issue date ※ 19 June 2022 |
Cite • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|