Author: Bospflug, R.    [Böspflug, R.]
Paper Title Page
TUPOMS015 Proposal of a Girder Realignment Test in PETRA III 1435
 
  • M. Schaumann, I.V. Agapov, R. Bartolini, M. Bieler, R. Böspflug, D. Einfeld, M.G. Hoffmann, J. Keil, L. Liao, G. Priebe, M. Schlösser, R. Wanzenberg
    DESY, Hamburg, Germany
 
  PETRA IV can benefit from the fine control of the girders that carry the storage ring elements to achieve the design beam performance. Based on the corrector magnet strength pattern it is desired to realign girders to stay within the alignment tolerances. In the current PETRA III configuration, the girders in the Max von Laue Hall are equipped for remote alignment, however, those have not been moved since their initial installation and the alignment system is currently not connected to the control system. In preparation for PETRA IV, a movement test of one of the PETRA III girders should confirm the ability to safely and precisely remote control the equipment based on an optics model that describes the effect of the girder movement on the orbit. This paper studies the feasibility of this test and prepares an initial mock-up experiment to be performed on a spare girder.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-TUPOMS015  
About • Received ※ 07 June 2022 — Revised ※ 13 June 2022 — Accepted ※ 14 June 2022 — Issue date ※ 15 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOMS029 Status of the PETRA IV Machine Project 1475
 
  • R. Bartolini, I.V. Agapov, A. Aloev, R. Bacher, R. Böspflug, H.-J. Eckoldt, J. Hauser, M. Hüning, P. Hülsmann, N. Koldrack, B. Krause, L. Lilje, G. Loisch, R. Onken, A. Petrov, S. Pfeiffer, J. Prenting, H. Schlarb, M. Thede, M. Tischer
    DESY, Hamburg, Germany
 
  DESY is planning the upgrade of PETRA III to a fourth generation light source, providing high brightness, quasi diffraction limited hard X-ray photons. The project is underpinned by the construction of a new storage ring PETRA IV, based on a 20 pm accelerator lattice using a hybrid 6-bend achromat concept. We review here the status of the machine project, the latest development in the different technical subsystems, the status of the engineering integration and the plans for the implementation of the new ring in the existing PETRA III tunnel.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-TUPOMS029  
About • Received ※ 14 June 2022 — Revised ※ 14 June 2022 — Accepted ※ 16 June 2022 — Issue date ※ 21 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)