Author: Bertrand, Q.
Paper Title Page
MOPOST011 CEA Contribution to the PIP-II Linear Accelerator 74
 
  • N. Bazin, J. Belorgey, S. Berry, J. Drant, O. Napoly, A. Raut, P. Sahuquet, C. Simon
    CEA-DRF-IRFU, France
  • S. Arsenyev, Q. Bertrand, P. Brédy, E. Cenni, C. Cloué, R. Cubizolles, H. Jenhani, S. Ladegaillerie, A. Le Baut, A. Moreau, O. Piquet
    CEA-IRFU, Gif-sur-Yvette, France
  • O. Napoly
    Fermilab, Batavia, Illinois, USA
 
  The Proton Improvement Plan II (PIP-II) that will be installed at Fermilab is the first U.S. accelerator project that will have significant contributions from international partners. CEA joined the international collaboration in 2018, and will deliver 10 low-beta cryomodules as In-Kind Contribution to the PIP-II project, with cavities supplied by LASA-INFN and power couplers and tuning systems supplied by Fermilab. This paper presents the CEA scope of work that includes the design, manufacturing, assembly and tests of the cryomodules and the upgrade of the existing infrastructures to the PIP-II requirements.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-MOPOST011  
About • Received ※ 13 June 2022 — Revised ※ 13 June 2022 — Accepted ※ 15 June 2022 — Issue date ※ 25 June 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOTK002 Results of the RF Power Tests of the ESS Cryomodules Tested at CEA 1186
 
  • O. Piquet, S. Berry, A. Bouygues, E. Cenni, G. Devanz, C. Madec, C. Mayri, P. Sahuquet
    CEA-DRF-IRFU, France
  • C. Arcambal, Q. Bertrand, P. Bosland, T. Hamelin
    CEA-IRFU, Gif-sur-Yvette, France
  • M.J. Ellis
    STFC/DL/ASTeC, Daresbury, Warrington, Cheshire, United Kingdom
  • P. Pierini
    ESS, Lund, Sweden
  • D. Sertore
    INFN/LASA, Segrate (MI), Italy
 
  Eight of the medium and high beta cryomodules deliv-ered to ESS by CEA are tested at CEA before delivery; the two medium and high beta prototypes and the three first of each type of the series. The goal of these tests is to validate the assembly and the performances on few cryomodules before the next cryomodules of the series are delivered to ESS. This paper summarizes the general results obtained during the tests at 2 K and at high RF power, Pmax = 1.1 MW. The cavities reach the ESS re-quirements, Eacc = 16.7 MV/m (Medium beta) and 19.9 MV/m (High beta) with an efficient compensation of the Lorentz detuning by the piezo tuner over the full RF pulse length of 3.6 ms at 14 Hz. After the successful tests at CEA, the first cryomodules have been shipped to ESS where the final acceptance test are performed.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2022-TUPOTK002  